What the public record actually shows for Bolsover. Every figure below is measured or published, with its sample and its date. Nothing here is an estimate, and none of it predicts what a particular application will do.

How long decisions took

Median weeks from validation to decision, counted from the council’s own register. A median means half of decisions took longer, so it is a middle, not a target.

Application typeMedianDecisions counted
All other applications6.3 weeks81

Measured over applications decided 01/07/2024 to 13/07/2026.

Housing Delivery Test

Bolsover measured 205% in the 2025 Housing Delivery Test — consequence: None.

MHCLG records 1,277 homes delivered against a three-year requirement of 622.

This ratio is driven by the size of the requirement, not by high absolute delivery. At a requirement this small, one strategic site can move the percentage by hundreds of points, so compare the homes delivered rather than the percentage.

Published by MHCLG on 2026-08-17. This is the most recent measurement published, not a current-year figure, and it is the number that determines whether the presumption in favour of sustainable development is engaged.

Planning appeals in Bolsover

12 allowed in full, 13 dismissed, from 25 planning appeals decided for Bolsover between 01/01/2021 and 31/07/2026.

We do not turn that into a percentage: under 100 decided appeals, a rate looks like a finding and behaves like noise. The counts are the honest form. This is not a statement that no appeals succeeded. Only refused applications get appealed, so these are a self-selected minority of decisions.

What this page is not

It does not tell you what constrains a particular site in Bolsover. Designations sit on land, not on councils. For that, run a free check on the site itself: it names every designation on or beside the boundary, states when each dataset was last collected, and says plainly where a record is not published rather than showing you a clear result.

Check a site in Bolsover — free

Appeal outcomes from the Planning Inspectorate appeals database, England only, Open Government Licence v3.0, release of 2026-08-31. Decision speed measured from council registers by PF & Co. Housing Delivery Test © MHCLG, Open Government Licence v3.0. All 274 authorities.