How long planning decisions take in Stockport
What the public record actually shows for Stockport. Every figure below is measured or published, with its sample and its date. Nothing here is an estimate, and none of it predicts what a particular application will do.
How long decisions took
Median weeks from validation to decision, counted from the council’s own register. A median means half of decisions took longer, so it is a middle, not a target.
| Application type | Median | Decisions counted |
|---|---|---|
| Major schemes | 33.9 weeks | 57 |
| All other applications | 6 weeks | 128 |
Measured over applications decided 1 July 2024 to 13 July 2026.
Housing Delivery Test
Stockport measured 43% in the 2025 Housing Delivery Test — consequence: Presumption.
MHCLG records 1,457 homes delivered against a three-year requirement of 3,408.
It fell well short of its housing requirement. Under the August 2026 Framework that is one of the routes into policy S5(1)(j), which can support housing meeting an evidenced unmet need outside a settlement, subject to that policy’s own tests. It is a point in your favour, not a decision.
Published by MHCLG on 17 August 2026. This is the most recent measurement published, not a current-year figure.
Planning appeals in Stockport
26 allowed in full, 43 dismissed, from 69 planning appeals decided for Stockport between 1 January 2021 and 31 July 2026.
We do not turn that into a percentage: under 100 decided appeals, a rate looks like a finding and behaves like noise. The counts are the honest form. This is not a statement that no appeals succeeded. Only refused applications get appealed, so these are a self-selected minority of decisions.
What this page is not
It does not tell you what constrains a particular site in Stockport. Designations sit on land, not on councils. For that, run a free check on the site itself: it names every designation on or beside the boundary, states when each dataset was last collected, and says plainly where a record is not published rather than showing you a clear result.
Check a site in Stockport — freeAppeal outcomes from the Planning Inspectorate appeals database, England only, Open Government Licence v3.0, release of 31 August 2026. Decision speed measured from council registers by PF & Co. Housing Delivery Test © MHCLG, Open Government Licence v3.0. All 274 authorities.